CMS Tracker Alignment activities during LHC Long Shutdown 2
The strategies for and the performance of the CMS tracker alignment during the 2021-2022 LHC commissioning preceding the Run 3 data-taking period are described. The results of the very first tracker alignment after the pixel reinstallation, performed with cosmic ray muons recorded with the solenoid...
Autor principal: | |
---|---|
Lenguaje: | eng |
Publicado: |
2022
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.22323/1.414.0633 http://cds.cern.ch/record/2841558 |
Sumario: | The strategies for and the performance of the CMS tracker alignment during the 2021-2022 LHC
commissioning preceding the Run 3 data-taking period are described. The results of the very
first tracker alignment after the pixel reinstallation, performed with cosmic ray muons recorded
with the solenoid magnet off are presented. Also, the performance of the first alignment of the
commissioning period with collision data events, collected at center-of-mass energy of 900 GeV,
is presented. Finally, the tracker alignment effort during the final countdown to LHC Run 3 is
discussed. |
---|