Shaft Excavation in Frozen Ground at Point 5

Construction work on the 112 MCHF civil engineering contract started at Point 5 in August 1998. The new surface buildings and underground structures are necessary to accommodate the CMS detector for the LHC Project. The principal underground works consist of two new shafts, two parallel caverns sepa...