BE 400/18 kV Substation Renovation Project
The 400/18 kV SPS main substation was designed for the 400 GeV SPS project and was commissioned in 1974. It has been upgraded several times to form the present 400/66/18 kV SPS and LEP transmission power comprising 490 MVA and 240 MVAR installed power. The beginning of the LHC project and the obsole...