Design and construction of the tensioned ties for UX15 cavern vault
Due to the programme constraints for the UX15 cavern set by CERN, it has been necessary to complete the concrete lining of the vault prior to the excavation of the bench. The vault lining is therefore being temporarily suspended from a number of pre-tensioned high capacity multi-strand tensioned tie...