Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string

The IFMIF LIPAc cryomodule houses eight half-wave resonators and eight solenoids which will be assembled on a support frame in clean room. Due to the short lattice defined by beam dynamics constraints, there is not much room between two elements for the operators’ hands to connect them. In order to...

Descripción completa

Detalles Bibliográficos
Autores principales: Bazin, Nicolas, Chambrillon, Janic Kevin, Devanz, Guillaume, Dzitko, Hervé, Hardy, Philippe, Neyret, Jerome, Servouin, Christophe, Toral, Fernando
Lenguaje:eng
Publicado: 2015
Materias:
Acceso en línea:https://dx.doi.org/10.18429/JACoW-SRF2015-TUPB107
http://cds.cern.ch/record/2288273
_version_ 1780956153869500416
author Bazin, Nicolas
Chambrillon, Janic Kevin
Devanz, Guillaume
Dzitko, Hervé
Hardy, Philippe
Neyret, Jerome
Servouin, Christophe
Toral, Fernando
author_facet Bazin, Nicolas
Chambrillon, Janic Kevin
Devanz, Guillaume
Dzitko, Hervé
Hardy, Philippe
Neyret, Jerome
Servouin, Christophe
Toral, Fernando
author_sort Bazin, Nicolas
collection CERN
description The IFMIF LIPAc cryomodule houses eight half-wave resonators and eight solenoids which will be assembled on a support frame in clean room. Due to the short lattice defined by beam dynamics constraints, there is not much room between two elements for the operators’ hands to connect them. In order to test, optimize and validate the clean room assembly procedures and the associated tools, a test bench, consisting of a frame, a little bigger than one eight of the final support has been manufactured. In order to start the tests before the delivery of the actual key components of the cryomodule, a dummy cavity, solenoid and coupler were manufactured and will be used to perform tests outside and inside the clean room to validate the assembly procedure and the tools. The mock-up will then be used to train the operators for the assembly of the whole string.
id oai-inspirehep.net-1482137
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2015
record_format invenio
spelling oai-inspirehep.net-14821372019-09-30T06:29:59Zdoi:10.18429/JACoW-SRF2015-TUPB107http://cds.cern.ch/record/2288273engBazin, NicolasChambrillon, Janic KevinDevanz, GuillaumeDzitko, HervéHardy, PhilippeNeyret, JeromeServouin, ChristopheToral, FernandoDevelopment of a test bench to prepare the assembly of the IFMIF LIPAC cavity stringAccelerators and Storage RingsThe IFMIF LIPAc cryomodule houses eight half-wave resonators and eight solenoids which will be assembled on a support frame in clean room. Due to the short lattice defined by beam dynamics constraints, there is not much room between two elements for the operators’ hands to connect them. In order to test, optimize and validate the clean room assembly procedures and the associated tools, a test bench, consisting of a frame, a little bigger than one eight of the final support has been manufactured. In order to start the tests before the delivery of the actual key components of the cryomodule, a dummy cavity, solenoid and coupler were manufactured and will be used to perform tests outside and inside the clean room to validate the assembly procedure and the tools. The mock-up will then be used to train the operators for the assembly of the whole string.oai:inspirehep.net:14821372015
spellingShingle Accelerators and Storage Rings
Bazin, Nicolas
Chambrillon, Janic Kevin
Devanz, Guillaume
Dzitko, Hervé
Hardy, Philippe
Neyret, Jerome
Servouin, Christophe
Toral, Fernando
Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string
title Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string
title_full Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string
title_fullStr Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string
title_full_unstemmed Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string
title_short Development of a test bench to prepare the assembly of the IFMIF LIPAC cavity string
title_sort development of a test bench to prepare the assembly of the ifmif lipac cavity string
topic Accelerators and Storage Rings
url https://dx.doi.org/10.18429/JACoW-SRF2015-TUPB107
http://cds.cern.ch/record/2288273
work_keys_str_mv AT bazinnicolas developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT chambrillonjanickevin developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT devanzguillaume developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT dzitkoherve developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT hardyphilippe developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT neyretjerome developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT servouinchristophe developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring
AT toralfernando developmentofatestbenchtopreparetheassemblyoftheifmiflipaccavitystring