Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans

During Run 1 of the LHC, one of the injection kicker magnets caused occasional operational delays due to beam induced heating with high bunch intensity and short bunch lengths. In addition, there were also sporadic issues with vacuum activity and electrical flashover of the injection kickers. An ext...

Descripción completa

Detalles Bibliográficos
Autores principales: Barnes, M J, Adraktas, A, Bregliozzi, G, Goddard, B, Ducimetière, L, Salvant, B, Sestak, J, Vega Cid, L, Weterings, W, Yin Vallgren, C
Lenguaje:eng
Publicado: 2017
Materias:
Acceso en línea:https://dx.doi.org/10.1088/1742-6596/874/1/012101
https://dx.doi.org/10.18429/JACoW-IPAC2017-WEPVA100
http://cds.cern.ch/record/2276060
_version_ 1780955269596971008
author Barnes, M J
Adraktas, A
Bregliozzi, G
Goddard, B
Ducimetière, L
Salvant, B
Sestak, J
Vega Cid, L
Weterings, W
Yin Vallgren, C
author_facet Barnes, M J
Adraktas, A
Bregliozzi, G
Goddard, B
Ducimetière, L
Salvant, B
Sestak, J
Vega Cid, L
Weterings, W
Yin Vallgren, C
author_sort Barnes, M J
collection CERN
description During Run 1 of the LHC, one of the injection kicker magnets caused occasional operational delays due to beam induced heating with high bunch intensity and short bunch lengths. In addition, there were also sporadic issues with vacuum activity and electrical flashover of the injection kickers. An extensive program of studies was launched and significant upgrades were carried out during Long Shutdown 1 (LS 1). These upgrades included a new design of beam screen to reduce both beam coupling impedance of the kicker magnet and the electric field associated with the screen conductors, hence decreasing the probability of electrical breakdown in this region. This paper presents operational experience of the injection kicker magnets during the first years of Run 2 of the LHC, including a discussion of faults and kicker magnet issues that limited LHC operation. In addition, in light of these issues, plans for further upgrades are briefly discussed.
id oai-inspirehep.net-1611212
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2017
record_format invenio
spelling oai-inspirehep.net-16112122021-02-09T10:05:53Zdoi:10.1088/1742-6596/874/1/012101doi:10.18429/JACoW-IPAC2017-WEPVA100http://cds.cern.ch/record/2276060engBarnes, M JAdraktas, ABregliozzi, GGoddard, BDucimetière, LSalvant, BSestak, JVega Cid, LWeterings, WYin Vallgren, COperational experience of the upgraded LHC injection kicker magnets during Run 2 and future plansAccelerators and Storage RingsDuring Run 1 of the LHC, one of the injection kicker magnets caused occasional operational delays due to beam induced heating with high bunch intensity and short bunch lengths. In addition, there were also sporadic issues with vacuum activity and electrical flashover of the injection kickers. An extensive program of studies was launched and significant upgrades were carried out during Long Shutdown 1 (LS 1). These upgrades included a new design of beam screen to reduce both beam coupling impedance of the kicker magnet and the electric field associated with the screen conductors, hence decreasing the probability of electrical breakdown in this region. This paper presents operational experience of the injection kicker magnets during the first years of Run 2 of the LHC, including a discussion of faults and kicker magnet issues that limited LHC operation. In addition, in light of these issues, plans for further upgrades are briefly discussed.CERN-ACC-2017-310oai:inspirehep.net:16112122017
spellingShingle Accelerators and Storage Rings
Barnes, M J
Adraktas, A
Bregliozzi, G
Goddard, B
Ducimetière, L
Salvant, B
Sestak, J
Vega Cid, L
Weterings, W
Yin Vallgren, C
Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans
title Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans
title_full Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans
title_fullStr Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans
title_full_unstemmed Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans
title_short Operational experience of the upgraded LHC injection kicker magnets during Run 2 and future plans
title_sort operational experience of the upgraded lhc injection kicker magnets during run 2 and future plans
topic Accelerators and Storage Rings
url https://dx.doi.org/10.1088/1742-6596/874/1/012101
https://dx.doi.org/10.18429/JACoW-IPAC2017-WEPVA100
http://cds.cern.ch/record/2276060
work_keys_str_mv AT barnesmj operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT adraktasa operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT bregliozzig operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT goddardb operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT ducimetierel operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT salvantb operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT sestakj operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT vegacidl operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT weteringsw operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans
AT yinvallgrenc operationalexperienceoftheupgradedlhcinjectionkickermagnetsduringrun2andfutureplans