Status and commissioning plans for LHC Run 2. The RF system.

The paper presents the work done on the LHC RF system during Long Shutdown 1 (LS1). On the High Level side we have replaced a cryomodule (four cavities, beam 2), which could not operate reliably at the design voltage (2 MV per cavity). The upgrade of klystron collectors has been completed and new cr...