Cargando…
Status and commissioning plans for LHC Run 2. The RF system.
The paper presents the work done on the LHC RF system during Long Shutdown 1 (LS1). On the High Level side we have replaced a cryomodule (four cavities, beam 2), which could not operate reliably at the design voltage (2 MV per cavity). The upgrade of klystron collectors has been completed and new cr...
Autores principales: | , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
CERN
2014
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/2295096 |