Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast

The new CERN linear accelerator Linac4 started the installation phase in 2010 after the delivery of the new building and tunnel by the civil engineering and was inaugurated six years later. It will be connected to the CERN accelerators chain and replace the current proton linear accelerator, Linac2,...