Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast

The new CERN linear accelerator Linac4 started the installation phase in 2010 after the delivery of the new building and tunnel by the civil engineering and was inaugurated six years later. It will be connected to the CERN accelerators chain and replace the current proton linear accelerator, Linac2,...

Descripción completa

Detalles Bibliográficos
Autores principales: Coupard, Julie, Berjillos, Aurelio, Corso, Jean-Pierre, Foraz, Katy, Nicquevert, Bertrand, Paulat, Emmanuel, Vretenar, Maurizio
Lenguaje:eng
Publicado: 2018
Materias:
Acceso en línea:https://dx.doi.org/10.18429/JACoW-IPAC2018-TUPAF044
http://cds.cern.ch/record/2666856
_version_ 1780962043008909312
author Coupard, Julie
Berjillos, Aurelio
Corso, Jean-Pierre
Foraz, Katy
Nicquevert, Bertrand
Paulat, Emmanuel
Vretenar, Maurizio
author_facet Coupard, Julie
Berjillos, Aurelio
Corso, Jean-Pierre
Foraz, Katy
Nicquevert, Bertrand
Paulat, Emmanuel
Vretenar, Maurizio
author_sort Coupard, Julie
collection CERN
description The new CERN linear accelerator Linac4 started the installation phase in 2010 after the delivery of the new building and tunnel by the civil engineering and was inaugurated six years later. It will be connected to the CERN accelerators chain and replace the current proton linear accelerator, Linac2, during the second long shut-down (LS2) of the Large Hadron Collider (LHC) in 2019. This paper aims to summarize the schedule evolution through the different phases of installation, from general services to machine installation, highlight the key factors that contributed to drive the schedule (safety, logistics and integration) and describe the coordination study of the future connection (integration, schedule, logistics, constraints and priorities).
id oai-inspirehep.net-1690641
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2018
record_format invenio
spelling oai-inspirehep.net-16906412019-09-30T06:29:59Zdoi:10.18429/JACoW-IPAC2018-TUPAF044http://cds.cern.ch/record/2666856engCoupard, JulieBerjillos, AurelioCorso, Jean-PierreForaz, KatyNicquevert, BertrandPaulat, EmmanuelVretenar, MaurizioSchedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection ForecastAccelerators and Storage RingsThe new CERN linear accelerator Linac4 started the installation phase in 2010 after the delivery of the new building and tunnel by the civil engineering and was inaugurated six years later. It will be connected to the CERN accelerators chain and replace the current proton linear accelerator, Linac2, during the second long shut-down (LS2) of the Large Hadron Collider (LHC) in 2019. This paper aims to summarize the schedule evolution through the different phases of installation, from general services to machine installation, highlight the key factors that contributed to drive the schedule (safety, logistics and integration) and describe the coordination study of the future connection (integration, schedule, logistics, constraints and priorities).oai:inspirehep.net:16906412018
spellingShingle Accelerators and Storage Rings
Coupard, Julie
Berjillos, Aurelio
Corso, Jean-Pierre
Foraz, Katy
Nicquevert, Bertrand
Paulat, Emmanuel
Vretenar, Maurizio
Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast
title Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast
title_full Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast
title_fullStr Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast
title_full_unstemmed Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast
title_short Schedule Evolution of the Linac4 Installation During the Lifetime of the Linac4 Project and Connection Forecast
title_sort schedule evolution of the linac4 installation during the lifetime of the linac4 project and connection forecast
topic Accelerators and Storage Rings
url https://dx.doi.org/10.18429/JACoW-IPAC2018-TUPAF044
http://cds.cern.ch/record/2666856
work_keys_str_mv AT coupardjulie scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast
AT berjillosaurelio scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast
AT corsojeanpierre scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast
AT forazkaty scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast
AT nicquevertbertrand scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast
AT paulatemmanuel scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast
AT vretenarmaurizio scheduleevolutionofthelinac4installationduringthelifetimeofthelinac4projectandconnectionforecast