Evaluation of Heat Stress in Construction Site of Metro Rail in Chennai

INTRODUCTION: Tunnel boring machine (TBM) is used for constructing a tunnel. Worn out cutting tools have to be changed under difficult working conditions. Temperature is high and the work is strenuous. Work is often carried out under increased atmospheric pressure to ward off water ingress. Workers...

Descripción completa

Detalles Bibliográficos
Autores principales: Kulkarni, Ajit C., Srinivasan, Krishnan
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Medknow Publications & Media Pvt Ltd 2018
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC6176705/
https://www.ncbi.nlm.nih.gov/pubmed/30319232
http://dx.doi.org/10.4103/ijoem.IJOEM_51_18
Descripción
Sumario:INTRODUCTION: Tunnel boring machine (TBM) is used for constructing a tunnel. Worn out cutting tools have to be changed under difficult working conditions. Temperature is high and the work is strenuous. Work is often carried out under increased atmospheric pressure to ward off water ingress. Workers are at a very high risk. AIM: To evaluate heat stress during hyperbaric intervention on TBM during Chennai Metro Rail construction. METHODOLOGY: One hundred and eighty-eight miners after a thorough medical examination worked under increased atmospheric pressure for more than 45,000 man hours. Mitigating actions to protect workers by reducing temperature and increasing ventilation. Medical monitoring was done to identify and treat potential victims. RESULTS: 52° C was the highest temperature recorded. Most times work was carried out at a temperature range of 34–45° C. CONCLUSIONS: Motivations of monetary gains, reduced working hours, and food supplements played a major role in work execution without any untoward incidence.