Sediment and morphological changes along Yangtze River’s 500 km between Datong and Xuliujing before and after Three Gorges Dam commissioning

The impoundment of the Three Gorges Dam on the Yangtze River begins in 2003 and a full pool level is first attained in 2010. This process leads to reciprocal adjustments in flow discharge, sediment transport and morphology downstream of the dam. Based on 26-year recorded hydrologic data 1990–2015 an...