Estimating the economic cost of setting up a nuclear power plant at Rooppur in Bangladesh
Bangladesh government is in the final stage of setting up one nuclear power plant with two units at Rooppur, Ishwardi, each having 1200 MW capacity, to be launched in 2023 to meet the energy shortage urgently. The financial cost of the project is the US $12.65 billion. The primary purpose of this pa...